Project Schedule

Terminology
  • Precedence
  • Concurrence
  • Leads & Lag time
  • Milestones

 

Scheduling Techniques

  • Mathematical Analysis
    • Network Diagram

  • Bar Chart


Network Diagram


  • Activity on Arrow Network
    • Event is binary
    • Activity can be partially complete

  • Activity on Node Network
    • Events are shown in activity on node network unless they are milestones
    • Milestones are points in the project at which major portions of the work are completed

 

Reason for scheduling
  • Ensuring that the deadline can be met

  • How the project should be managed


Critical Path

  • Def: the series of activities that determines the duration of the project
  • All project have a critical path

  • Critical path must do


PERT (Program Evaluation and Review Technique)

  • Based on idea that estimates are uncertain

  • Uses an "expected value"


    How to estimate

    Optimistic (ex. 5Weeeks)
    Most likely (ex. 7weeks)
    Pessimistic (ex. 10weeks)


    PERT Formula

    te = ( a + 4m + b ) / 6
te expected time
aoptimistic time estimate
mmost likely time estimate
bpessimistic time estimate

 
ex. (5w + 4*7w + 10w) / 6 = 7.16w

 