03/03/2010
Project Schedule
Terminology
- Precedence
- Concurrence
- Leads & Lag time
- Milestones
Scheduling Techniques
Mathematical Analysis
- Network Diagram
- Network Diagram
Bar Chart
Activity on Arrow Network
- Event is binary
- Activity can be partially complete
- Event is binary
Activity on Node Network- Events are shown in activity on node network unless they are milestones
- Milestones are points in the project at which major portions of the work are completed
- Events are shown in activity on node network unless they are milestones
Reason for scheduling
- Ensuring that the deadline can be met
How the project should be managed
- Def: the series of activities that determines the duration of the project
- All project have a critical path
Critical path must do
- Based on idea that estimates are uncertain
Uses an "expected value"
How to estimate
Optimistic (ex. 5Weeeks)
Most likely (ex. 7weeks)
Pessimistic (ex. 10weeks)
PERT Formula
te = ( a + 4m + b ) / 6
te | expected time |
a | optimistic time estimate |
m | most likely time estimate |
b | pessimistic time estimate |
ex. (5w + 4*7w + 10w) / 6 = 7.16w